Covered Entryway, Driveway & Narthex Remodel

More photos will be posted as construction continues
of the Covered Entryway, Driveway & Narthex Remodel. 
Please check back!

Week 29 & 30: May 3 - 7 & May 10 - 14 2021
Lighting and electrical fittings have been installed at the drop-off area.

Two sets of stairway rails have been installed in the parking areas.

Gravel and blacktop are delivered.

  

Week 27: April 19 - 23, 2021
The roof of the covered walkway
in it's final steps toward completion.

Covered Walkway ceiling  and trim is painted.
 
Two sets of steps between the parking areas are made ready with concrete forms.
 
Sidewalk, curbs & bicycle pad
are made ready with forms for concrete.

Week 26: April 12-16 2021

Cement walkway and eastside portico is poured.
 
Interior of the walkway ceiling
is made ready for final wood work.

Exterior trim is installed around the new brick archway.

Sidewalk frame is set and poured with cement near the playground.
 
Exterior new portico double doors are installed.
 

Week 25 April 5-9 2021
1. Two side walks were poured
2. Glass installation for the vestry & vestebule
3. Covered Entryway Arch installed

Side walk closest to the main sanctuary:
 
 
 

Side walk leading from the Covered Entryway toward parking areas:
 

  

Glass installation for the exterior of the vestry and vestibule entrance.
 

Construction of the archway
The arrival of expected materials!
The metal support system was intricately assembled on the ground,
and careful installed at the arch with many measurements.
Once the metal frame was welded,
brick could be securely cemented to create
the archway.

The archway's metal support system is carefully assembled and installed.
  
   
Side anchors of the archway consisting of the metal support system, are installed into the existing brick columns.
  
The archway's metal support system is welded together. 
 
Brick is cemented over and around the underlying metal arch support.
 
As planed, the archway is completed by the end of the day-Friday & ready for Week 26!
 
Scaffolding used to complete the Covered Entryway arch
during Week 25 will be removed in Week 26.
 

Week 20 & 21/March 1-5, 8-12 2021
The snow has melted with the coming spring temps!

 
The coatroom and vestment have been painted.
The plastic curtain barrier (that went up on Day One/Oct. 19, 2020) has been taken down
and the narthex between the Main Entrance and Church office is painted.
 

Week 16, 17 & 18/Feb. 1-5, 8-12, 15-19, 2021
The coat room gets electricity, air ducts and drywall.
These before (left) and after (right) photos show that progress!
Before and After: ceiling section of the new coat room.
 
Before and After: corner/ceiling of the new coat room.
 
Before and After:
Looking into the interior room (from inside the new coat room).
 
Before and After: Interior of the new coat room.
Looking through the newly constructed doorway
between the coat room and the narthex.
 

Week 14 & 15/Jan. 18-22, 25-29, 2021
Winter snow in the midst of construction.
 


Plywood has been added over the coat room and portico vestment frame.
 

 
What was the porch is now enclosed for the coat room.
 
The Entance area: main entrance doors remain. The porch to the left of the doors is enclosed with plywood for the new coat room.

Electrical wiring and air duct work begins in the coat room and portico vestment.
  

 

Week 13/Jan. 11-15 2021
The underside of the walkway and entryway are ready to be covered with a cut to fit plywood ceiling.
  

  
Electrical outlet boxes and mounts ready to be wired (ceiling and wall).
 

Weeks 11 & 12/Dec. 28-30 & Jan. 4-8 2021
Covered Entryway and Covered Drop-off columns are brick finished.

Trim and roof are carefully placed.

The foundation for the brick arch frame is created.

The portico vestment and coat room framing is made ready.

Drain lines are dug and installed.
 

Week 10/December 21-23, 2020
Scaffolding is set and concrete pillars are prepared for brick.




   

 

 

Week 7/November 30-December 4, 2020
The covered entryway
- the section which will allow cars to pass through is framed with lumber.




 

Week 6/November 23-25 Thanksgiving week!
During week 3 concrete cement was poured in the area designated for the new coat room. This week more cement was poured for the the coat room floor.

The covered entryway was framed with lumber.
   

Week 5/November 16-20
The new coat room foundation.

Steel beams and lumber for the covered walkway arrived.

Covered walkway construction over the week included sunny days!



Week 4/November 9-13:
Bulldozing the land between the Sanctuary and Parking area:
Before:
 

After:

Concrete blocks are laid in the entryway. The beginnings of the columns that will support the covered entryway.
  

More soil is removed

Week 3/November 2-6:
Concrete cement is poured in the area designated for the new coat room.
 

The mapped walkway is surveyed by the crew.

Stakes mark were the walkway columns will be placed.

Grates are placed over the column foundations of the walkway.

The walkway column foundations closest to the parking area are poured with cement.

Parking lot islands begin transformation with heavy equipment.
  

Fill dirt has a new purpose in the Community Garden.

Week 2/October 26-28:

  
The porch and slate rubble is hauled away.

Fencing went up.

Week 1 Today, the construction work began, October 19th 2020.
The workman put up a plastic curtain barrier in the Narthex,

 
...and jackhammered the slate from the old coat room, on day 2.
Day 3. Cement is removed from the porch.
   

Planning together:
Neil Furr, Phil Sutton & part of the construction crew.

The main south entrance (#1) is temporarily closed and an alternative entrance is made at the gym door/off the preschool playground for both preschool and Sunday Worship.

The west entrance near the Historic Sanctuary (#5) remains open.